MINING TOOL

Excavator Productivity Calculator

Estimate excavator cubic metres and tonnes per hour from bucket size, cycle time, fill factor and job efficiency.

Excavator Productivity Calculator

FREE ONLINE TOOL

Inputs

Educational planning estimate, not a certified design.

STEP BY STEP

How to use excavator productivity calculator

  1. Compare your result with the worked example.
  2. Check the assumptions and limitations.

WHEN IT HELPS

Common uses

  • Use this excavator production estimate to compare equipment and plan loading operations. The result describes loose material handled per productive hour under your assumptions.

Method and assumptions

Cycles/h = 3,600 / cycle seconds × efficiency. m³/h = cycles/h × bucket m³ × fill factor. t/h = m³/h × loose bulk density.

Worked example

A 2.5 m³ bucket, 90% fill, 30-second cycles and 75% efficiency produces 202.5 m³/h. At 1.8 t/m³ the estimate is 364.5 t/h.

Limitations

Capacity is loose-volume capacity, not in-situ bank volume. Do not mix swell and density bases. Spotting, queueing, truck availability and haulage can constrain real output.

Frequently asked question

Does excavator capacity equal mine production?

No. Actual mine production may be limited by hauling capacity, delays, material conditions and operational constraints.

Excavator Productivity Calculator — Calculation guide