Formula and units
Advance per round (m) = drilled round length (m) × pull efficiency ÷ 100. Shift advance = advance per round × completed rounds. Pull efficiency is surveyed advance divided by drilled round length; use a measured value from the same heading and comparable conditions.
Worked example
A 3.0 m drilled round with 85% pull gives 3.0 × 0.85 = 2.55 m advance. Two completed rounds give 5.10 m for the shift. Compare the estimate with face survey measurements, not the drill plan alone.
Assumptions and limits
The result is a production estimate, not a blast design. Rock structure, drilling accuracy, burden relief, charging, firing, support and interruptions affect pull. The calculator does not prescribe hole patterns, explosive quantities or safe operating limits.