MINING TOOL
Development Advance per Round Calculator
Estimate development advance per blast round and shift advance from drilled length, measured pull efficiency and rounds per shift.
Development Advance per Round Calculator
FREE ONLINE TOOLWHEN IT HELPS
Common uses
- Convert drilled round length and measured pull into advance metres.
- Prepare a transparent development shift estimate from site inputs.
IN PRACTICE
Example
A 3.0 m round at 85% pull gives 2.55 m advance per round. Two rounds give 5.10 m per shift.
GOOD TO KNOW
What does pull efficiency mean?
Pull efficiency is the measured advance divided by drilled round length, expressed as a percentage. Use site data for the relevant heading and conditions. The estimate does not design a blast or recommend explosives.
Planning estimate only. Use measured site pull efficiency and confirm actual advance by survey. This calculator does not design blasts or recommend explosives.